DOCUMENT REVISION HISTORY
Date | Version | Page(s) | Description | Author |
11/28/2017 | 1.0 | All | Initial publication | FedRAMP PMO |
10/20/2021 | 2.0 | All | Document updated to provide clarity on updated processes and information | FedRAMP PMO |
02/15/2024 | 3.0 | All | Updated to add clarity and align with Rev 5 updates made to FedRAMP guidance documents and templates. | FedRAMP PMO |
Understanding the FedRAMP Marketplace
FedRAMP Agency Liaison Program
Initial FedRAMP Agency Authorization
Partnering for Initial FedRAMP Authorization
Use the FedRAMP PMO for Support
Introduction
1.0 Why Use FedRAMP
- Federal agencies have the opportunity to save money and time by adopting innovative cloud services to meet their critical mission needs.
- Federal agencies are required by law to protect federal data stored in the cloud. Federal agencies do this by authorizing cloud services that demonstrate compliance with one of the FedRAMP security baselines.
- The FedRAMP Policy Memo states that “each Executive department or agency shall use FedRAMP when conducting risk assessments, security authorizations, and granting ATOs [Authority to Operate] for all federal executive department or agency use of cloud services.”
- FedRAMP provides a standardized approach to security authorization in accordance with Federal Information Security Modernization Act (FISMA) and National Institute for Standards and Technology (NIST) security requirements. One of our main goals is to prevent agencies from reinventing the wheel. The ‘do once, use many’ approach promotes reuse of standardized security assessments to save agencies time and resources.
- FedRAMP facilitates collaboration across the federal government and regularly provides guidance and support to help federal agencies through the authorization process.
- Email intake@fedramp.gov to learn about any upcoming events or new resources available for agencies.
2.0 Why This Document
- This playbook is designed as a reference for agencies pursuing an initial FedRAMP authorization. For information on how to reuse an existing authorization, reference the FedRAMP Reusing Authorizations for Cloud Products Quick Guide.
- The purpose of this playbook is to provide federal agencies with guidance, best practices, and tips to successfully implement the FedRAMP authorization process.
- The overall goal of this playbook is to promote transparency and consistent expectation management between federal agencies and cloud service providers (CSPs).
- Reference this playbook throughout the process in conjunction with ongoing communication with the FedRAMP Program Management Office (PMO).
3.0 What You Will Get From This Document
- A description of each step of the process
- Federal agency, CSP, and third party assessment organization (3PAO) roles and responsibilities
- Best practices and considerations for working effectively with stakeholders and executing the security review
- FedRAMP resources and templates available for your reference
Understanding the FedRAMP Marketplace
The FedRAMP Marketplace provides a searchable, sortable database of cloud service offerings (CSOs) that have achieved a FedRAMP designation. Federal agencies can use the FedRAMP Marketplace to find secure cloud tools that meet their mission needs.
Agencies are encouraged to use the Marketplace as a resource to:
- Research CSOs that are FedRAMP Authorized, FedRAMP Ready, or FedRAMP In Process
- Research federal agencies that use FedRAMP Authorized CSOs
- Research FedRAMP recognized 3PAOs
Reusing FedRAMP Authorized CSOs
CSOs that are FedRAMP Authorized are made available for government-wide use. Federal agencies can leverage the security documentation of a FedRAMP Authorized CSO by following the process outlined in FedRAMP’s Reusing Authorizations for Cloud Products Quick Guide.
4.0 FedRAMP Designations
FedRAMP defines three different designations for CSOs: FedRAMP Ready, FedRAMP In Process, and
FedRAMP Authorized.
FedRAMP Ready: A designation provided to CSOs which indicates that a 3PAO attests to a CSO’s security capabilities, and that a FedRAMP Readiness Assessment Report (RAR) has been reviewed and deemed acceptable by the FedRAMP PMO. FedRAMP Ready indicates a CSO has a high likelihood of successfully completing an initial FedRAMP authorization with the Joint Authorization Board (JAB) or a federal agency.
FedRAMP In Process: A designation provided to CSOs that are actively working toward a FedRAMP authorization with either the JAB or a federal agency. For updates, agencies can either contact the cloud provider via the email address provided on the CSO’s FedRAMP Marketplace page, or reach out directly to the FedRAMP PMO via intake@fedramp.gov.
FedRAMP Authorized: A designation provided to CSOs that have successfully completed the FedRAMP authorization process with the JAB or a federal agency. FedRAMP Authorized CSOs are available for government-wide reuse.
You can learn more about FedRAMP’s Marketplace designations by reviewing the “Marketplace Designations” section on the About FedRAMP Marketplace webpage.
FedRAMP Agency Liaison Program
5.0 Program Overview
FedRAMP Agency Liaisons are dedicated points of contact within each federal agency who serve as the bridge connecting an agency and the FedRAMP PMO. The FedRAMP Agency Liaison Program established a voluntary community of trained individuals that will serve as a unified voice across federal agencies as they teach and
facilitate FedRAMP processes and procedures. The goals of the FedRAMP Agency Liaison Program are to promote faster and more efficient authorizations and enable agency liaisons to train others within their agencies about the FedRAMP process.
6.0 Program Benefits Include:
- Increased collaboration by facilitating a direct line of communications between federal agencies, bureaus, and the FedRAMP PMO
- Increased awareness of FedRAMP by improving understanding of FedRAMP and the FedRAMP Marketplace throughout the federal government
- Greater efficiency by establishing a single point of expertise that can lead to faster authorizations and less use of resources over time
- Improved visibility to increase transparency into program updates and strategic initiatives
7.0 How to Leverage FedRAMP Agency Liaisons
FedRAMP Agency Liaisons can answer general questions about FedRAMP, the FedRAMP reuse process, the initial authorization process, and continuous monitoring (ConMon). Liaisons have been trained to provide seminars and training sessions on these topics within their agencies. In addition, liaisons can provide information about upcoming training sessions hosted by the FedRAMP PMO.
Liaisons can also provide clarification on the status of cloud vendors within their own federal agencies, and can help answer questions about how to secure partnership for initial FedRAMP authorization at their agencies.
Every CFO Act agency has an agency liaison who can serve as the subject matter expert and resource for questions about FedRAMP. Many sub agencies and departments have designated their own liaisons as well. If you are unsure who your agency liaison is, please contact intake@fedramp.gov. If your agency does not have a liaison identified, the FedRAMP PMO can help you designate a point of contact and enroll your agency in the program.
Initial FedRAMP Agency Authorization
Below is the recommended FedRAMP initial agency authorization process. The following sections of this playbook outline each step of the process.
* The full security assessment may be prepared in advance of the Authorization phase, or completed during the Authorization phase. This is dependent on the federal agency’s review approach.
Partnering for Initial FedRAMP Authorization
Federal agencies can partner with a CSP for an initial FedRAMP authorization if they would like to use a CSO that is not currently FedRAMP Authorized. The rest of this playbook explains the initial FedRAMP authorization process, providing guidance and tips for success at each point along the way.
8.0 Common Questions About Partnership
Answers to the frequently asked questions below can be found under the “Federal Agencies” tab of the FAQs page on FedRAMP.gov. If you have additional questions about the responsibility of an initial authorizing agency, please first reach out to your agency’s FedRAMP Agency Liaison before reaching out to the FedRAMP PMO at intake@fedramp.gov.
Preparation
9.0 Readiness Assessment
The FedRAMP Readiness Assessment is required for CSPs pursuing a JAB Provisional Authority to Operate (P-ATO) and is highly recommended for CSPs pursuing a FedRAMP authorization with a federal agency partner. CSOs categorized at the Moderate or High impact levels can achieve a FedRAMP Ready designation after successful completion of a FedRAMP Readiness Assessment.
FedRAMP Ready indicates that a CSP has utilized the services of a FedRAMP recognized 3PAO to conduct a FedRAMP Readiness Assessment, and the 3PAO has determined that the CSP is fully ready to pursue (and likely to achieve) a FedRAMP authorization for the CSO. The results of a FedRAMP Readiness Assessment are documented in a FedRAMP provided Readiness Assessment Report (RAR) template. The RAR is submitted to the FedRAMP PMO for review and approval. Once approved, the RAR is made available to agencies via the FedRAMP secure repository.
To understand the scope of a FedRAMP Readiness Assessment, federal agencies can review the FedRAMP Moderate RAR Template or the FedRAMP High RAR Template. At a high level, the FedRAMP Readiness Assessment is primarily focused on the status of technical control implementations versus the status of documentation. While some CSPs may have a fully developed system security plan (SSP), at the time of the assessment, a completed SSP is not required. During the FedRAMP Readiness Assessment, 3PAOs validate the CSP’s ability to meet specific federal mandates (e.g., the use of FIPS 140 validated encryption), the CSP’s ability to satisfy technical security requirements, and the CSP’s maturity in areas such as change management and ConMon.
Federal agencies should consider partnering with a CSO that has achieved the FedRAMP Ready designation, if the CSO meets the federal agency’s mission needs. FedRAMP Ready indicates that the CSP has done most of the heavy lifting and just needs a federal agency to partner with them to pursue an initial FedRAMP authorization.
10.0 Pre-Authorization
During the Pre-authorization phase, the federal agency and CSP agree to partner on a FedRAMP authorization. The federal agency and CSP then work together to prepare for and develop a plan for the agency authorization, and hold a formal kickoff meeting.
10.1 Partnership Establishment
During the Partnership Establishment phase, the federal agency agrees to partner with a CSP to pursue an initial FedRAMP authorization. If you are thinking about partnering with a CSP, consider the following steps and, if needed, schedule a call with your FedRAMP Agency Liaison, or the FedRAMP PMO, to talk through the process:
Clearly define your federal agency’s mission needs and specific requirements for a CSO, and begin researching possible providers.
Understand the sensitivity of the data that will be used with the CSO. To categorize your data, review the NIST Federal Information Processing Standards (FIPS) Publication 199, Standards for Security Categorization of Federal Information and Information Systems.
Review the FedRAMP Marketplace to see if there is a CSO that meets your mission needs and is able to provide the right level of security given the data. If there is a CSO on the FedRAMP Marketplace that interests you, contact the FedRAMP PMO to learn more about the CSO’s authorization status.
If you find a CSO that meets your mission needs, but is not on the FedRAMP Marketplace, meet with the associated CSP to determine the organization’s willingness and commitment to pursue a FedRAMP authorization. If the CSP would like to learn more about the FedRAMP process, direct them to the FedRAMP CSP Authorization Playbook. If the CSP has not already done so, instruct the CSP to complete FedRAMP’s CSP Information Form to schedule a preliminary intake call with the FedRAMP PMO.
Consider the following when determining the CSP’s readiness for pursuing a
FedRAMP authorization:
- Fully built and functional system
- Mature organizational and security processes
- Committed CSP leadership team
- Proven maturity (CMMI Level 3+, ISO organizational certifications)
- Other certifications (SOC2, ISO27001, PCI, etc.)
- CSP’s ability to meet federal agency-specific requirements above the FedRAMP security control baseline (if applicable)
10.2 Authorization Planning
The purpose of the Planning phase is to set up the authorization for success. The authorization planning process is a collaborative effort between the federal agency and CSP. During the Planning phase, stakeholders will:
Establish a collaborative and transparent working relationship. This includes:
- Identifying CSP and federal agency project leads/primary points of contact
- Deciding how CSP and federal agency teams will communicate and collaborate. The FedRAMP PMO recommends establishing a recurring meeting (at least bi-weekly) to ensure the project stays on track and that everyone remains accountable for their respective areas of responsibility
- Identify federal agency team members assigned to review the authorization package
- Federal agency reviewers should have knowledge of the NIST Risk Management Framework and experience reviewing FISMA and/or FedRAMP authorization packages. FedRAMP highly recommends taking the FedRAMP ISSO on-demand training module, which is designed to help federal agency reviewers understand the process for reviewing a FedRAMP authorization package
- Determine how the CSP and 3PAO will share authorization package deliverables with the federal agency
- Develop a method for capturing and tracking agency reviewer comments/questions
- Determine the federal agency’s internal process for reaching an authorization decision and granting an ATO
- Determine the federal agency’s approach for reviewing the authorization package as described below:
Just-In-Time Linear Approach | All Deliverables Provided Simultaneously |
Each FedRAMP deliverable builds upon another, starting with the SSP. The SSP and appendices, security assessment plan (SAP), and security assessment report (SAR) are completed in a linear fashion, obtaining feedback from the federal agency once each deliverable is produced. In turn, modifications are made to each deliverable, based on the federal agency’s review. Once the deliverable is finalized and accepted by the federal agency, work begins on the next deliverable. |
All FedRAMP deliverables (i.e., SSP/appendices, SAP, SAR, and plan of action and milestones (POA&M)) are completed and submitted to the federal agency at once. The federal agency reviews all deliverables together and works collaboratively with the CSP and 3PAO. This approach resembles how authorizations are completed for a FedRAMP JAB authorization. |
Helpful Tip: The FedRAMP PMO recommends the Just-In-Time approach as it is a more iterative and agile approach that may prevent rework after 3PAO testing has occurred. |
10.3 Work Breakdown Structure and In Process Request
As your federal agency finalizes the Authorization Planning phase, complete the following actions:
- Complete a work breakdown structure (WBS), in partnership with the CSP. After the completion of the WBS, please send it to the FedRAMP PMO at intake@fedramp.gov for review and feedback.
- Submit a FedRAMP In-Process Request to the FedRAMP PMO via intake@fedramp.gov. The completion of this form indicates to the FedRAMP PMO that your federal agency is ready to begin coordinating a kickoff meeting with the CSP, FedRAMP PMO, and 3PAO (optional and recommended). It also indicates that you have reviewed and approved the WBS and 3PAO testing is scheduled within six (6) months. At this point, the FedRAMP PMO will provide a copy of the kickoff meeting presentation template to the CSP.
- Instruct your CSP to begin working on the kickoff meeting presentation. A copy of the CSP’s completed presentation must be sent to the FedRAMP PMO via intake@fedramp.gov for review and feedback prior to confirming a date and time for the kickoff meeting.
See the FedRAMP In Process section on the About FedRAMP Marketplace webpage for more information about the FedRAMP In Process request, WBS, and the full criteria for a CSP to be listed as In Process. Your federal agency’s FedRAMP Liaison will be able to assist in the above actions listed above.
10.4 Kickoff Meeting
The purpose of the kickoff meeting is to formally begin the FedRAMP agency authorization process by introducing key team members, reviewing the CSO, and ensuring all stakeholders are aligned on the overall process. While the FedRAMP PMO coordinates and facilitates kickoff meetings, these meetings are meant to be in service of the CSP and federal agency partnership. Review FedRAMP’s Kickoff Briefing guidance to understand the full scope of a FedRAMP-facilitated kickoff meeting.
At the conclusion of the kickoff meeting, all stakeholders will have a shared understanding of:
- The overall authorization process, milestones, deliverables, roles and responsibilities, and schedule
- The roles and responsibilities of all project team members including federal agency, CSP, and 3PAO personnel
- The CSO’s purpose and function, authorization boundary, data flows, known security gaps and plans for remediation, federal agency-specific requirements, customer responsible controls, and areas that may require federal agency risk acceptance
- The federal agency’s process for reviewing the authorization package and reaching a risk-based authorization decision
- The FedRAMP PMO’s process for reviewing the authorization package from the perspective of government-wide reuse
- Best practices and tips for success
Helpful Tip: If there are any additional internal administrative requirements, such as uploading to any governance, risk management, and compliance (GRC) tools, they should be communicated at the kickoff meeting and built into the authorization timeline. |
Authorization
11.0 Full Security Assessment
The CSP is responsible for delivering a security package that is clear, complete, concise, and consistent to adequately describe how they implement security controls for their system using the required FedRAMP Templates. The federal agency’s role, in this step of the process, is to review the documentation provided by the CSP and provide feedback where deemed necessary. The ultimate goal is for the CSP to provide a security package that other federal agencies can leverage for review.
During the Full Security Assessment phase, the 3PAO performs an independent security assessment of the system. Depending on the federal agency’s review approach determined in the Authorization Planning phase, the federal agency may review and approve the SSP and SAP prior to the start of the 3PAO assessment.
During this step, the 3PAO tests and validates the CSP’s implementation of security controls, validates vulnerability scans, and performs penetration testing. At the conclusion of the assessment, the 3PAO develops a SAR, which documents the results of the security assessment and includes a recommendation for FedRAMP authorization.
The CSP will then develop a POA&M based on the SAR findings. The POA&M documents the CSP’s plan and timeline for remediating residual risk that remained at the conclusion of the security assessment.
12.0 Agency Authorization Process
12.1 Agency Review of Security Authorization Package
During this phase, the federal agency team conducts a review of the CSO authorization package that includes: the SSP and appendices, SAP, SAR, and POA&M. The purpose of the review is to ensure that the authorization package clearly and accurately reflects the security posture of the CSO in order for the federal agency authorizing official
(AO) to make an informed risk-based authorization decision. A helpful resource is the FedRAMP Agency ISSO on-demand training module to help federal agency reviewers understand the process for reviewing a FedRAMP authorization package.
The FedRAMP PMO recommends establishing a regular cadence of meetings that include the federal agency, CSP, and 3PAO throughout the quality and risk review in order to address federal agency questions and concerns in real time. This might include longer in-person working sessions to address specific areas of the CSO.
12.2 SAR Debrief
The purpose of the SAR debrief is to help inform the federal agency’s risk review of the CSO. During the SAR debrief, the 3PAO presents the results of the security assessment, the CSP presents the plan and timeline for remediating residual risk, and the FedRAMP PMO describes the remaining milestones and tips for success. The FedRAMP
PMO coordinates and facilitates the SAR debrief; however, it is meant to be in service of the CSP and federal
agency partnership.
At the conclusion of the SAR debrief, all stakeholders will have a shared understanding of:
- The 3PAO’s assessment approach, methodology, and schedule
- The scope of testing, which includes validation of the authorization boundary and data flows
- The assessment results and residual risk
- The CSP’s plan and timeline for remediating residual risk
- Deviation requests that require federal agency approval (e.g., risk adjustments and false positives)
- Operationally required risks that require federal agency risk acceptance (e.g., services or components essential to the operation of the CSO, but excluded from the tested boundary)
- The federal agency’s process for reviewing the authorization package and reaching a risk-based authorization decision
- The FedRAMP PMO’s process for reviewing the authorization package from the perspective of government-wide reuse
- Best practices and tips for success
12.3 Remediation
To ensure the authorization package clearly and accurately reflects the security and risk posture of the CSO, the CSP and 3PAO may be required to address documentation gaps or inconsistencies identified by the federal agency
review team.
Examples include:
- Inconsistencies across SSP control narratives
- Inconsistencies between the boundary diagram, data flow diagrams, and SSP narrative
- Inconsistencies between control narratives and what is validated by the 3PAO and described in the FedRAMP Security Test Case Procedures Workbook
- Inconsistencies between the SAR and POA&M
In addition, the CSP may be asked to remediate or mitigate open risks in order to achieve an acceptable level of risk for the federal agency AO.
In some cases, the 3PAO may be required to perform delta testing to validate risk remediations or perform additional testing if the federal agency review team identifies gaps in the initial assessment scope. For example, if the 3PAO failed to validate the encryption status of federal data/metadata at rest and in transit or failed to test a component essential to the operation of the CSO.
The federal agency’s review of remediation work can happen on an iterative, or linear basis, depending on the federal agency’s preference. It is important to maintain constant communication between the federal agency and CSP throughout the remediation process to ensure that the gaps and other areas of concern are being addressed to the federal agency’s satisfaction.
At the end of the Remediation phase, the federal agency, CSP, and 3PAO should conduct a formal close-out meeting to review all changes, address questions in real time, and obtain approval to move forward to the final review and ATO phase.
12.4 Agency Final Review and ATO
During this phase, the federal agency review team finalizes its review of the authorization package and the federal agency AO issues an ATO for the CSO. The FedRAMP PMO provides an ATO letter template that federal agency AOs are encouraged to use. The ATO letter is sent to the CSP and info@fedramp.gov.
The process for closing out the review and issuing an ATO varies from federal agency to agency. The implementation, testing, and documentation of customer controls in the federal agency’s GRC tool typically occurs during this
phase, but may occur later in the authorization process, after the ATO for the CSO is issued. As described in
the Authorization Planning section, the federal agency’s process and timeline for reaching an authorization
decision and issuing an ATO should be defined early in the process and communicated to all stakeholders to
manage expectations.
12.5 FedRAMP PMO Review
Once the federal agency AO issues the ATO letter, the FedRAMP PMO performs a review of the authorization package to determine suitability for government-wide reuse. The scope of the FedRAMP PMO’s review includes:
- A quality review to ensure the authorization package clearly and accurately represents the security and risk posture of the CSO; while the initial authorizing agency conducts a quality review of the authorization package, the FedRAMP PMO’s review is considered ‘a final set of eyes’ to ensure uniformity across all packages listed on the FedRAMP Marketplace
- A security review to ensure compliance with FedRAMP requirements and standards
- A risk review to identify weaknesses or deficiencies that must be addressed before the FedRAMP Marketplace status is changed to FedRAMP Authorized
After the ATO letter is received, the following steps are performed to get to a FedRAMP Authorized designation:
- CSP and 3PAO upload current versions of package deliverables to the FedRAMP secure repository for Low and Moderate packages, or to the CSP’s repository for High packages
- CSP completes and submits FedRAMP Initial Authorization Package Checklist to info@fedramp.gov
- FedRAMP PMO verifies that all package deliverables are uploaded
- Package is placed in the FedRAMP PMO review team’s queue. Packages are reviewed in the order they are received
- Low and Moderate package reviews typically take 10 business days from the start of review (High packages can take up to 20 days); this assumes there are no significant quality issues that may slow down the review
- FedRAMP PMO review team sends draft review report to all stakeholders (CSP, 3PAO, and federal agency)
- Draft report documents findings identified during FedRAMP PMO’s review, and any areas that require clarification
- FedRAMP PMO coordinates review meeting to walk through findings and clarification requests, as well as plans for remediation by CSP/3PAO
- Draft report is sent at least one week prior to the meeting
- CSP/3PAO address findings and resubmits package; notifies the FedRAMP PMO via pmo-review@fedramp.gov
- FedRAMP PMO performs gap review
- Communicates remaining gaps or recommends authorization to FedRAMP leadership
- Once approved, FedRAMP Marketplace designation is changed to FedRAMP Authorized
Continuous Monitoring
Throughout the Authorization phase, CSPs are required to maintain the system, which includes performing ConMon activities. The CSP’s ability to demonstrate a mature ConMon process is one of the areas evaluated during the 3PAO’s assessment, and during the federal agency and FedRAMP PMO’s review of the authorization package. Failure to demonstrate a mature ConMon process will prevent or delay a FedRAMP Authorized designation.
Once the Authorization phase is complete and the CSO achieves a FedRAMP Authorized designation, the CSP:
- Continuously monitors the security posture of the CSO
- Provides federal agencies with information needed to make risk-based decisions about the ongoing authorization of the CSO
The CSP is responsible for implementing the ConMon processes and tools to maintain an acceptable security posture. Each federal agency that issues an ATO for a CSO is responsible for reviewing the CSP’s ConMon activities to ensure the security posture remains sufficient for its own use and supports an ongoing authorization. This includes reviewing the monthly POA&M, approving deviation requests/significant changes, and reviewing the results of the annual assessment.
These activities are described in the FedRAMP Continuous Monitoring Strategy Guide. Please refer to this document for a more in depth overview of these activities.
13.0 Collaborative ConMon
CSPs with more than one federal agency customer are required to implement a collaborative ConMon approach, intended to streamline the ConMon process and potentially minimize duplicative efforts in a way that helps each federal agency still perform their due diligence related to ConMon. This approach is described in the FedRAMP Collaborative ConMon Quick Guide. Collaborative ConMon benefits federal agencies by allowing them to share responsibility for ConMon oversight, and it benefits the CSP by creating a central forum for addressing questions and achieving consensus related to deviation requests, significant change requests, and the annual assessment, versus having to coordinate with each federal agency separately.
13.1 ConMon Best Practices
- Authorization Planning: Start talking to the CSP about ConMon early in the process, especially if you have ConMon requirements that exceed FedRAMP’s requirements. If you do, you should make the CSP aware of those requirements before authorizing the system.
- Continuous Monitoring: Ask the CSP to hold a monthly ConMon meeting. As additional federal agency customers begin using the CSO, ask the CSP to hold a monthly collaborative ConMon meeting.
- The meeting should be held at least one week after the monthly ConMon deliverables are submitted. This will give the federal agency team time to review the deliverables and come to the meeting ready with questions and recommendations for approvals of deviation requests or significant change requests
- A monthly ConMon meeting agenda might include:
- Discussion of past due POA&Ms
- Deviation requests pending approval
- Significant change requests (i.e., planned changes, changes pending approval, and status of implementation and testing)
- Status of annual assessment
- Continuous Monitoring Accountability: Think about how you will hold the CSP accountable for meeting ConMon requirements. The FedRAMP Continuous Monitoring Performance Guide explains the actions the FedRAMP JAB takes when a FedRAMP JAB Authorized CSP fails to maintain an adequate ConMon capability. Section 3 of this guide also provides recommendations for processes that agencies should use to perform oversight of CSOs authorized via the FedRAMP agency authorization path.
Use the FedRAMP PMO for Support
The FedRAMP PMO is dedicated to supporting agencies and CSPs through the initial FedRAMP authorization process. FedRAMP encourages leveraging your federal agency’s FedRAMP Liaison, as they have a deep knowledge of the FedRAMP process and requirements for partnering with a CSP for an initial FedRAMP authorization. FedRAMP’s customer success team is also available to address your federal agency’s questions as you consider partnering with a CSP. Please reach out to FedRAMP at intake@fedramp.gov.